How much will the fit out cost?

Based on the fit out going into a new open plan office, the range of prices will be

  • Standard fit out i.e. back of house standard $300.00 - $450.00 per m2
  • Medium fit out i.e. middle management with areas of back of house $400.00 - $600.00 per m2
  • High quality fit out i.e. top management $600.00 – $1,000.00 per m2

Strip out and make good $75 - $125.00 per m2
Back to Top »

How long will it take?

  • estimating the costs from completed plans approx 1-2 weeks
  • procurement timing approx 1 week to organize labour etc.
  • time on site approx 5 weeks based on an 800 – 1000 m2 fit out

Back to Top »

How can we save time?
Negotiated works can be up to 30% quicker than traditional contracts.
Back to Top »

What are the normal payment terms?
We normally ask 15% deposit with the remaining 85% invoiced on a fortnightly or monthly basis with payment within 14 days.
Back to Top »

What is your minimum and maximum project values?
We have no minimum contract value and no maximum contract value.
Back to Top »

What insurances do you hold?

  • Workers Compensation
  • Combined Public and product liability to $20m
  • Contract work all risk insurance
  • Transport insurance

Back to Top »

Do you guarantee your completion date?
We are proud of state that we have a 100% record on finishing all works on programmed.
Back to Top »

What is your quality like?
The fact that approx 80% of our works are for existing clients or are from recommendations are testament to the fact that our quality is first class.
Back to Top »

What are the costs of the mechanical, electrical, fire and hydraulic services?
On average the services element of a contract amounts to between 40 – 60 % of the overall costs.